School district embarks on bond program

Northview Public Schools (NPS) is an award-winning district in Grand Rapids, Mich., acknowledged for the high caliber of its graduates and the high quality of its staff. After engaging Plante Moran Realpoint (PMR), formerly Plante Moran Cresa, to provide enrollment projections and a comprehensive facility condition assessment, the district learned about PMR’s bond planning services and brought on our experts to assist in assembling the PQ application and planning the bond information campaign.

In 2020, voters approved the $36.7 million bond aimed to make districtwide improvements targeting its three elementary schools and two middle schools. The improvements encompassed a range of areas including playgrounds, the performing arts center, bathrooms, track and learning spaces with the objective to provide upgrades to building infrastructure, security, and technology.

Owner’s representative delivers results for school district

With the bond funds secured, PMR was engaged for owner’s representation services to oversee the bond program. PMR helped the district with procuring professional services and contract negotiations before overseeing the design and construction activities throughout the four-year program.

Our team’s value as an advocate for NPS was highlighted by our ability to condense the timeline of the bond program to avoid unnecessary construction costs. Our strategic phasing allowed the district to complete the bond projects a year earlier than planned. In addition, with proactive planning during the pandemic’s historically high construction cost escalation, PMR helped the district avoid 15% to 20% in additional costs.

Renovated school facilities enjoyed by community

During an extended period of uncertainty in the supply chain and construction market, NPS fully recognized the value of an owner’s representative in PMR when the program was completed in 2023, a year earlier than planned. NPS students and staff are fully realizing the investment of their community. Major projects from the 2020 bond program include:

  • New secure entrances, playgrounds, and busses
  • Renovated classrooms, bathrooms, and track for elementary and middle schools
  • Performing arts center improvements
  • Improved air conditioning
  • Parking lot/parent drop-off upgrades

If your district is planning a capital program, give our experts a call today. We provide the technical knowledge and experience of working with 100+ school districts so that you can focus on what matters most — education.


Want great space like this? Contact:


Warren Mott High School Exterior

Warren Consolidated Schools

Warren, MI

Since 2000, Warren Consolidated Schools, the tenth largest school district in Michigan, has engaged Plante Moran Realpoint for bond planning and owner’s representative services for four bond programs totaling more than $500 million of site work, renovations, and additions.

Case Study / 2 min read

View project
Photo of GRPS Southwest Side High School Entrance, a capital project completed as part of the 2015 $175 million bond program with help from K12 owner's representative Plante Moran Cresa

Grand Rapids Public Schools

Grand Rapids, MI

Grand Rapids Public Schools builds state-of-the-art educational institution with owner’s representative Plante Moran Realpoint, serving students and community members as a space for collaboration.

Case Study / 2 min read

View project
Van Buren Schools Image

Van Buren Public Schools

Belleville, MI

Plante Moran Realpoint's pre-bond planning and program management services have saved Van Buren Public Schools millions over its bond programs and sinking fund projects.

Case Study / 2 min read

View project
Novi Community School District high school athletic building and track, as seen from outside

Novi Community School District

Novi, MI

To keep its mission of “a commitment to excellence,” Novi Community School District used funds from two voter-approved bonds over eight years to make improvements across district facilities and build a new Early Childhood Education Center.

Case Study / 1 min read

View project
Photo of Birmingham Public Schools MI Auditorium Exterior Entrance, a major project during the 2015 Bond Program with owner's representative Plante Moran Cresa

Birmingham Public Schools

Beverly Hills, MI

With funding from two bond programs spurring continuous facility improvements, Birmingham Public Schools solidifies its reputation as a top school district in Michigan.

Case Study / 2 min read

View project
Ypsilanti School District Image

Ypsilanti Public Schools

Ypsilanti, MI

In 2007, Ypsilanti Public Schools consisted of only 14 buildings, and the District was due for a much-needed renovation of its aging facilities and the addition of new facilities.

Case Study / 1 min read

View project